Why metal gutter system Roof-Stal

  • 30 years warranty
  • Made of 5 layers: steel, galvanized, passivation, primer, polyurethane coating
  • Two systems: System 125 with a depth of 80mm and System 150 with a depth of 92mm
  • High quality and durability
  1. Metal gutter
  2. Gutter joint
  3. Gutter hanger
  4. Gutter bracket straight
  5. Gutter bracket twisted
  6. Universal end cap
  7. Inner corner
  8. Outer corner
  9. Drop outlet
  10. Down pipe 1 m
  11. Down pipe 3 m
  12. T-pipe
  13. Pipe elbow
  14. Gutter shoe
  15. Down pipe clamping ring
  16. Down pipe joint
  17. Down pipe joint
  18. Screw /Clamp hook

Installation

More detailed information about the installation

Step 01 - Gutter positioning relative to the eaves
01

Correct installation must protect gutters against the impact of snow sliding down a roof. The upper edge of gutter flanging should be lowered below the extension of the roof slope surface.

Step 02 - Gutter positioning relative to the eaves
02

Extend a string between the highest and the lowest hanger. This helps determine the position of the rest of the hangers. The decline of the gutter towards the drain should be at least 2 mm per 1 m.

Step 03 - Gutter positioning relative to the eaves
03

Gutter hangers should be mounted directly to the face board at 60 cm intervals. The first hanger should be placed 10 cm away from the roof edge.

Step 04 - Gutter positioning relative to the eaves
04

Rafter hooks should be installed at the maximum spacing of 1 m. The hooks should be distanced from the rafter edge at least 2 cm to allow free ventilation of the roof. Follow the diagram.

Step 05 - Cutting gutters and pipes to size
05

Use a soft pencil to outline the edge of the drop outlet on the surface of the gutter.

Step 06 - Connecting the gutter to the running outlet
06

The drain hole must be cut out by using scissors. The use of high-speed tools is not permitted! The diameter of the hole should be reduced by approximately 2,5 cm in relation to the previously marked edge of the drop outlet.

Step 07 - Installation of the gutter to the gutter fascia bracket
07

Stability of the drop outlet is ensured by four mounting elements, the so-called leaves, which must be bent deep into the gutter flanging.

Step 08 - Installation of the gutter to union elements
08

After latching the gutter joint on the rear flanging of the connected elemets, the joint with a gasket must be tightened and pressed from underneath. Only after pressing can the clamp be latched onto the front flanging and locked in place by bending the leaves.

Step 09 - Installation of gutter stopend
09

Connect corners to the gutters with gutter joints. It is necessary to use additional gutter hangers to stabilise the system. In order to ensure proper dilatation of the system, leave a 5 mm gap at the connection between the corner and the gutter. Mount the additional gutter hangers maximum 15 cm from the centre of the gutter joint.

Step 10 - Installation of drainage pipes
10

After screwing on the back part of the clamping ring, push the front part into the socket and screwed tight. Down pipe clamping rings should be installed at least every 2 m.

Step 11 - Installation of pipe brackets
11

Always use a spanner for screwing in or unscrewing the clamping ring when verticalisation of the down pipe.

Step 12 - Installation of pipe connector
12

Down pipes have a socket end. In case of a pipe with a cut off end, use a pipe joint.